Construction of initial part of East Wing Breakwater with a total length 800m & an adjacent Dyke with length of 250m.

It also consists of following works:

- Completion the protection layer of West Wing Breakwater

- Demolishing of old East Wing Breakwater (125m length)

- Construction of 3 Commodity loading Jetties with total length of 577m and the associated wall with a length of 58m

- Construction of 2 Oil Jetties with a length of 180m each

- A 12 hectare soil improvement in reclamation area with dynamic compact method.